Work Packages & Milestone Breakdown
WP-1: Foundation & DPC
100% DONE
Excavation, mass concrete blinding, strip footing, and German floor cast.
WP-2: Superstructure Blockwork
78% ACTIVE
9-inch sandcrete block walling up to lintel beam level, column rebar cages tied.
WP-3: Lintel Beam & Decking
SCHEDULED
Formwork assembly, rebar placement, and grade 25 concrete pour.
WP-4: Roofing & Finishes
SCHEDULED
Hardwood kingpost trusses, 0.55mm aluminum stone-coated roofing sheets.
Audited Material Deliveries & Waybill Register
PREVENTING WAREHOUSE-TO-SITE LEAKAGE
Chronological Visual Ledger
Verified Site Evidence (Watermarked Locations)
Showing authentic chronological logs captured via mobile camera
Log Note: "Work going on smoothly. Blockwork up to lintel beam level. Reinforcement checked and tied."
Log Note: "Walling verticality plumb-bob checked. 400 bags Dangote cement stacked under waterproof tarp."
Log Note: "Column starter bars tied with 10mm stirrups at 150mm centers according to structural plan."
Log Note: "Mortar joint thickness checked for 12mm tolerance. Superstructure walls rising steadily."
Log Note: "Pre-cast lintel beam installation over master bedroom window openings inspected."
Log Note: "Initial site setting out and foundation trenching completed to 1.2m solid bearing strata."